12 Matching Results

Explore Results

Reinforcing Steel Mat

Description: Caption says, "A-843 View of first mat of reinforcing steel beneath gallery. Note drainage and A-line grout nipples."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

River Outlet Pipe

Description: Caption says, "A-859 Closeup view of river outlet pipe at Pier 2 showing pipe and gate frame in place. Surfaces of concrete in old dam cleaned with air hammer and surfacer tool." Handwritten after caption is, "2nd from left, Harley Cargille, Blair. 1st of left - Odis Cross."
Date: April 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

South Dike

Description: Caption says, "A-896 View of South Dike taken from the left abutment after completion of initial construction to Elevation 1546."
Date: September 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Diversion Channel

Description: Caption says, "A-860 Concrete placed on left abutment to date on both sides of diversion channel. Concrete on left side at Elevation 1522 and on right side at Elevation 1519."
Date: April 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Excavation

Description: Caption says, "A-844 Primary excavation for right training wall. Embankment on right side is truck ramp leading off spillway apron." Hand written at the end of caption is, "Foreground: R. A. McCallum."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Concrete Placing

Description: Caption says, "A-857 Concrete in spillway portion at Elevation 1490.5. Note river outlet pipes installed in background."
Date: April 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Construction Operations

Description: Caption says, "A-845 General view of construction operations taken from left abutment. Concrete in left foreground is at Elevation 1476."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Concrete Placing

Description: Caption says, "A-858 View of concrete in spillway section at Elevation 1492.5 taken from right abutment. River outlet pipe at Pier 5 in background."
Date: April 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Truck Ramp

Description: Caption says, "A-848 Completed truck ramp on spillway apron for delivery of concrete to crane on dam."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Progress Picture

Description: Caption says, "A-898 View of Altus Dam taken from the left abutment after completion of the initial construction. Pipe handrails have been installed in location where no other protection was apparent. Note stoplogs in Canal trashrack structure in foreground."
Date: September 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Concrete Placing

Description: Caption says, "A-846 View of concrete placing operations taken from right abutment. Note portion of right training wall being placed monolithic with the dam."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie

Concrete Placing

Description: Caption says, "A-847 General view of concrete placing operations on dam. Fresh concrete is being placed to Elevation 1478."
Date: March 30, 1943
Creator: Breitenstein, Frank C.
Partner: Museum of the Western Prairie
Back to Top of Screen